SGGC doubles the production capacity of AeroAggregates LLC in Philadelphia
The production, which has already reached its limits after just one year, was successfully expanded to 130,000 m³/a. This was made possible, among other things, by the complete planning and optimal technical design already carried out in the first implementation step. The assembly and commissioning were carried out under high time pressure and with the requirement to interrupt the current production as short as possible.
In the second implementation step, AeroAggregates LLC also installed additional equipment in addition to the SGGC scope of supply. In this case a stacking conveyor system for optimal use of the storage areas was installed. Storaging capacity was doubled by this installation.